Power › Batteries2 min read

Quinbrook puts Supernode battery containers on stilts instead of concrete; 520 MW, 1858 MWh in operation

At the Supernode site in Brisbane, 36-tonne battery containers stand on pedestals, which Quinbrook says cut cost and sped up construction. Two stages are already operating.

Quinbrook puts Supernode battery containers on stilts instead of concrete; 520 MW, 1858 MWh in operation
Photo: reneweconomy.com.au

Infrastructure manager Quinbrook has two stages of its Supernode battery operating at Brendale, Brisbane, with a combined 520 MW and 1858 MWh, reneweconomy.com.au reports. A third stage is under way, and the site has room for a further 520 MW of expansion reneweconomy.com.aureneweconomy.com.aureneweconomy.com.auOpen source ↗.

On completion of the third stage, due in the December quarter of 2027 or the March quarter of 2028, nameplate capacity is to reach 780 MW and 3074 MWh. Investment so far is about $1.4 billion, with another $1.2-$1.5 billion possible.

Pedestals instead of a concrete slab

Each 36-tonne battery container at the site stands on small stilts, a "pedestal system". Quinbrook founder and managing partner David Scaysbrook calls the technique world-leading. He named the "quite outrageous" price of concrete as one motivation. According to him, the design also sped up construction, makes maintenance easier, lowers service costs and will simplify rehabilitation of the site. He said Quinbrook now uses the technique on its battery projects in the US and the UK.

Managing director James Allan described a second change. The containers were initially identical, with doors on the side, which required clearance between each unit. After discussions with CATL, the units became mirror images with facing doors, which reduced the clearance needed and freed up space reneweconomy.com.aureneweconomy.com.aureneweconomy.com.auOpen source ↗.

Performance and next stages

Each container is rated at 4 MW. Over 15 months of trials and operation, each delivered 4.073 MW, more than predicted, Scaysbrook said. The batteries now on site carry a 20-year warranty. For future stages, Quinbrook and CATL are developing the EnerQB 8-hour battery, which is to come with a 25-year warranty.

The site lies next to the South Pine substation and switchyard, through which as much as 80% of Queensland's power can pass. Scaysbrook did not say whether a data centre partner will join the site or whether it will be devoted entirely to a large battery, adding that he hoped to know by the end of the first quarter of next year. Quinbrook is also planning potentially three more supernodes with large batteries in eastern Australia, and CATL is likely to play a role.

Sources · 1

Found a mistake?
  1. ↩
RealTech on TelegramSubscribe

Read also

Up next

The next story opens automatically

More
Follow us

Type at least two letters — results appear instantly

↑↓to choose↵to openescto close