Hyvinkää, Finland, begins filling a 380,000 m³ gravel-pit reservoir for seasonal heat storage
Municipal company Hyvinkään Lämpövoima began filling a former gravel pit with water on 7 October 2026. Water heated in summer will supply district heating in winter.

Finland is building what is described as the world's largest open-basin underground thermal storage site at Kulomäki, near Hyvinkää, a town of 47,000 north of Helsinki. According to science-et-vie.com, on 7 October 2026 the municipal company Hyvinkään Lämpövoima Oy announced the start of filling a former gravel pit with water from the municipal network. science-et-vie.com
science-et-vie.comscience-et-vie.comOpen source ↗ The target volume is 380,000 cubic meters. The basin is as wide as five football fields and 20 meters deep. The reservoir is designed to store 18,000 MWh of heat.
The "largest in the world" label applies only to open basins, not to rock caverns such as those planned at Varanto.
How the heat reservoir works
In summer, renewable electricity in Finland is cheap. Electric boilers and waste heat from nearby industry are used to warm the water. Pumps draw cold water from the bottom and push it through a heat exchanger. The water returns warm through diffusers installed higher up. Depending on depth, the temperature ranges from 40 to 90 °C.
When cold weather arrives, the circuit reverses and the pumps feed Hyvinkää's district heating network. Three staged diffusers regulate the flows in both directions. The middle one is held in reserve for connecting a future heat pump, which would use low-temperature waste heat at around 70 °C. science-et-vie.com
science-et-vie.comscience-et-vie.comOpen source ↗
Schedule, cost and the Varanto comparison
The total cost is 33 million euros. The project is co-financed by Finland's Ministry of Economic Affairs and Employment. L&T Teollisuuspalvelut Oy is the main contractor for the first phase, and ISOPLUS Finland supplied the stainless steel piping.
Filling from the municipal network is expected to last until the end of April 2027. A permanent cover will then be installed. Hyvinkään Lämpövoima plans commissioning for autumn 2027. According to CEO Sanna Kytömäki, no accidents had occurred on the site by mid-October 2026.
The company aims to give up fossil fuels almost entirely. It expects heating prices to stabilise and says the transition would cut annual emissions by 4,400 tonnes of CO₂. science-et-vie.com
science-et-vie.comscience-et-vie.comOpen source ↗ According to EcoTicias, the reservoir could heat 20,000 people for a year at full load.
In Vantaa, the country's fourth-largest city, the Varanto project takes a different route. Vantaan Energia is excavating caverns in rock to create an underground thermal store. Deep groundwater pressure allows water to be kept at 140 °C without boiling. The planned capacity is 90 GWh, and the operator expects commissioning in 2030. "We went from a few hours to a full year of storage," said Esa Vakkilainen, professor emeritus at LUT University.