Power › Energy2 min read

BW ESS starts Hams Hall, Europe's largest battery by capacity at 1,243 MWh

The first phase of the West Midlands project brings 350 MW / 1,243 MWh online, reaching commercial operation 20 days after energisation.

Rows of containerised battery storage units at a grid battery station.
Illustrative photo of a grid-scale battery storage station; Hams Hall is not pictured.

Key points

  • Phase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation.
  • BW ESS says it is the largest battery in Europe by MWh.
  • Commercial operation came 20 days after energisation.
  • Phase two will raise the total to 400 MW / 1,424 MWh.

BW ESS has started commercial operations at the first phase of its Hams Hall battery energy storage system in North Warwickshire, England, adding 350 MW / 1,243 MWh to the grid bw-ess.comBW ESS newsbw-ess.comOpen source ↗energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗. The company announced the milestone in London on November 2 and says it makes Hams Hall the largest battery in Europe by storage capacity in MWh energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗renewableenergymagazine.comRenewable Energy Magazinerenewableenergymagazine.comOpen source ↗.

Hams Hall battery: phases and numbers

Phase one reached commercial operation just 20 days after energisation and was built "on budget and ahead of schedule", according to chief executive Erik Strømsø energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗. The site connects to the nearby Hams Hall 400 kV National Grid substation energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗.

ParameterPhase 1After phase 2
Power350 MW400 MW
Storage1,243 MWh1,424 MWh
Durationabout 3.5 habout 3.5 h

BW ESS says the full 400 MW / 1,424 MWh system will be able to support around 1.3 million homes for up to 3.5 hours energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗. Sungrow, Energy-IO, National Grid and the system operator NESO worked with the company on commissioning, testing and preparation for operation energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗.

How the project is financed

Revenue is underpinned by a 10-year floor agreement with EDF, which guarantees a minimum income while the battery trades in the market energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗. In October BW ESS secured debt financing for the full 400 MW / 1,424 MWh project from OCBC, Rabobank and Societe Generale energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗. Hams Hall joins the 331 MWh Bramley battery in Hampshire in the company's UK portfolio, and it is part of the 2.6 GWh Ardenham portfolio co-owned with AIP Management energy-pedia.comEnergy-pediaenergy-pedia.comPhase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWhOpen source ↗renewableenergymagazine.comRenewable Energy Magazinerenewableenergymagazine.comOpen source ↗.

Long-duration batteries of this size let the grid store surplus wind and solar output and release it during evening peaks, reducing curtailment of renewables.

Sources · 3

Found a mistake?
  1. ↩
  2. Energy-pediaenergy-pedia.compublication

    Phase one of Hams Hall brings 350 MW / 1,243 MWh into commercial operation; BW ESS says it is the largest battery in Europe by MWh

    ↩
  3. ↩
Add RealTech as a preferred source in Google

Read also

Up next

The next story opens automatically

More
Follow us

Type at least two letters — results appear instantly

↑↓to choose↵to openescto close