**Researchers from three Fraunhofer institutes designed a nationwide CO2 pipeline network for 2045 emissions, using scenarios and a physical simulation. No section of such a network is built or planned yet.**

![Fraunhofer institutes model a 7,000 km CO2 pipeline network for Germany, estimated at €17 billion](https://realtech.media/media/2026/11/707efbf004ecc6e2.jpg)
*Globetrotter19, Wikimedia Commons, CC BY-SA 3.0*

Researchers from three Fraunhofer institutes have developed a method for designing pipeline networks that carry carbon dioxide, according to spektrum.de. They combined assumptions about industrial development and CO2 volumes up to 2045 with a physical simulation of pipeline operation. The work was published in the Journal of CO2 Utilization. [1]

## Why a pipeline network is needed

Germany's carbon dioxide storage and transport law, adopted at the end of 2025, allows CO2 to be captured at certain industrial plants and stored under the North Sea. Cement and lime production, waste incineration and the chemical industry come into question, since their emissions are hard to avoid. [1]

Transport by truck, train or ship is possible, but trucks in particular carry only small quantities. Pipelines are considered the most effective way to move CO2 over long distances, with pumps compressing the gas to at least 85 bar so that it becomes liquid-like. [1] The federal government estimates that 7 to 10 years are needed to build the infrastructure. Today not a metre of the required pipe system is built or even planned. [1]

## What the proposed network looks like

According to the researchers, a suitable network would be about 7,000 kilometres long. The main lines would use pipes with an inner diameter of 66 centimetres, while smaller and cheaper pipes would suffice on branches. Pressures in the network would range from 85 to 180 bar, and pumping stations would be needed where pressure could drop below 85 bar. This combination needs the fewest pumps, which are among the most expensive components. [1]

The pipes alone cost roughly 2,500 to 3,500 euros per metre, and the researchers estimate total investment at about 17 billion euros. [1] The captured CO2 would go first to one of four ports, Wilhelmshaven, Bremerhaven, Brunsbüttel or Rostock, and then by ship to North Sea storage sites. CO2 from abroad was included in the scenario. [1]

The team also examined laying pipes along existing natural gas trunk routes, which could ease planning and permitting. The existing gas pipelines themselves cannot be reused because they would not withstand the pressure. Direct links between sources and storage would be more costly and complex. [1]

In a second scenario, the chemical industry would convert much of the CO2 with hydrogen into green methanol by 2045, for plastics or synthetic fuels. The researchers also calculated this case, in which the network could be sized for considerably smaller CO2 volumes. [1]